Go to SCD News table of contents


SCD News > Feature: March 10, 2004

NCAR Mesa Lab gets two standby power generators

Will vastly improve reliability and up-time of NCAR computers for user community

Generator system at Mesa Lab

The new generator system at the southeast corner of the Mesa Lab

Seven years from conception to implementation, a new standby generator system became operational at the NCAR Mesa Laboratory on 6 March 2004. The system will provide unlimited emergency power to the NCAR Computer Room, protecting millions of dollars worth of advanced computing and data storage equipment in case of electrical outages—a much-needed precaution in Boulder, Colorado, a city prone to high winds, heavy snows, and peak power demands during the heat of summer.

At the heart of the system, a pair of twin generators will be able to run the NCAR supercomputers and maintain electrical and cooling services for the computing facility. The generators will also support critical building functions such as emergency lighting, the boilers that heat the Mesa Lab, and cafeteria freezers.

Powered by California emissions-rated diesel engines that are extremely quiet and burn far cleaner than natural gas, the generators will run as long as they have fuel. Eight hours of fuel are stored onsite, and more can be delivered as needed.

The generators project, implemented by the Scientific Computing Division in cooperation with NCAR's Physical Plant Services, cost $2.1 million. SCD conducted preliminary studies in late 2000 and began custom-designing the system in spring 2001. Contractor bids were solicited in early 2003, with construction starting in in the fall. The generators arrived on 17 January 2004 and were fired up for the first time on 17 February. The system went online on 6 March.

A critical need

Aaron Andersen, manager of SCD's Operations and Infrastructure Support Section, began researching the possibility of backup power for NCAR in 1997. "That year I was promoted to head the infrastructure group, and I was amazed a facility of this size didn't have standby power capabilities. San Diego had its own generator facilities; Cornell had them, NERSC [the National Energy Research Supercomputing Center] had them.

"I wrote a proposal '97; it really picked up momentum when [current SCD director] Al Kellie came on board. He was struck like I was that we didn't have standby generator capabilities. He was coming from the Canadian Meteorological Centre, where they ran for almost 30 days on generators during the big ice storm, so he knew the need." (The Ice Storm of 1998 was the most expensive weather disaster in Canadian history.)

"There's a strong likelihood of power hits here because of our location. Chinooks, blizzards, heat waves—outages due to any one of these could cost considerable staff time and lost production for a week or more of science runs."

Aaron notes that SCD sustained three outages greater than two hours in the past year, resulting in thousands of CPU hours of lost simulation time. Last fall, the Computer Room was down for 17 hours due to high winds (see "High winds knock out power," and Aaron remembers a blizzard in 1995 that took out the regional power grid for nearly two days.

Gary New, an SCD computing facility engineer and technical lead on the generator project, agrees that lost production time on computer systems is disrupting and expensive. The March 2003 blizzard, Colorado's worst in 90 years, paralyzed the region and shut down all of UCAR. The bluesky, blackforest, babyblue, chinook, chinookfe, and mouache computing systems remained down for nearly 36 hours due to continuing power hits. (See "Digging out.")

"With an outage like that, the scientists are trying to get work done; it's costly in that it stops the flow of their work. So many jobs are in the queue, and if the computers are shut down, it backs up the queue. Also, computers are much happier when they run continuously, and shutdowns and powerups are difficult. An enormous amount of staff resources are required get the Computer Room back up and working."

Another reason emergency power is more important than it used to be is that NCAR has moved from proprietary vector computer systems to commodity-based clusters. The amount of staff time to recover a 1,200-processor cluster can be measured in weeks, as opposed to hours.

Clean, quiet, and environmental-friendly

From the project's outset, SCD was highly conscious of the need for a clean and quiet emergency power source.

"We, being the National Center for Atmospheric Research, wanted the best environmental-friendly system we could get," Gary explains. "We conducted a study that compared diesel to natural gas. It showed, hands down—and much to my surprise—that diesel burns much cleaner."

In the design specification, SCD required California emission standards for the generators. "These are some of the cleanest diesels installed anywhere," Aaron says, "the best emissions-rated engines that can be had."

They are also quiet. "A good one-quarter of the enclosure design is to mitigate noise," Aaron notes. "There's a combination of mufflers, sound dampening, baffles, and acoustic insulation. You can stand next to them and have a conversation."

"You won't find this at Midas," adds Gary, pointing to a photo of an eight-foot muffler. "These generators make less noise than a delivery truck."

A look under the hood

The generators themselves are huge. Each of the two "gensets," consisting of a generator, a V16 diesel engine, and a radiator, weighs 33,800 pounds—nearly 17 tons.

"We've got two 16-cylinder diesel engines," Gary says. "Each one puts out 1.5 megawatts of electricity. They're actually rated for 1,750 kilowatts, but at our altitude, it's 1,500."

Each genset sits on a skid atop a flat, 950-gallon fuel tank and is is hidden by a steel enclosure.

Other components of the generator system include a control switchboard, containing breakers that route the power, and a load bank—both also hidden by steel enclosures.

"The load bank, for all intents and purposes, is one huge toaster," Gary says. "It's got heating elements that induce an artificial load, so the generators can be tested once a month and run full speed without a live load."

"This keeps them in good operating order," Aaron adds. "It's just like if you have a classic car—you want to crank it up and take it for a spin every once and a while."

During acceptance testing, the generators ran for a combined total of 20 hours supporting the artificial load of the load bank, which is noisier than the generators. Some staff thought the sound was coming from the generators, but that was not the case. During an actual emergency, the generators would be driving the computing facility, not the load bank, and the area would be much quieter. The load bank will be employed only 30 minutes a month for preventive maintenance.

To minimize the aesthetic impact of the generator system and help it blend into its architectural surroundings, the steel enclosures are painted a muted, dusty pink to match the sandstone of the Mesa Lab.

More protection

"Until we installed the new generators, our backup power was strictly UPS—uninterruptible power supply," Aaron observes. "That's a battery backup, which is a finite power source that depends on how heavy the load is. At the loads we're running in the NCAR Computer Room, we'd be lucky to get 30 minutes of emergency power."

"The idea with generators," says Gary, "is that as long as you fuel them, the power source is unlimited. We have eight hours of fuel onsite, so we have eight hours to make a decision. During that time, we'll be supporting the Computer Room, but we'll also be picking up some kitchen equipment—for instance, the freezers, so we don't lose food—and other things for life-safety, such as the egress lighting and the boilers in the physical plant for heating and keeping the building going. The generators won't be any good if the building freezes. So we'll be supporting a minimum of building's mechanical systems."

Improved reliability = more science

"The main purpose of the new generators is to keep NCAR computing systems online, which will in turn advance science," Aaron concludes. "There's no question that it will vastly improve SCD's reliability and up-time as we deliver computing services to the user community."

—Lynda Lester

SCD News   ||  UCAR  ||  NCAR   ||   SCD   ||   Contact us   ||  Search
NCAR is managed by UCAR and sponsored by the National Science Foundation